PROGRESS OF CONSTRUCTION WORKS AT INNOVA APARTMENTS, BUILDINGS 6.4 AND 6.5 (MARCH 2015)

Wrocław, 12 March 2015

Buildings 6.4 and 6.5 at the Innova Apartments are 5% complete. The sheet pile walls have been put in place and now they are being anchored. Earthworks are 70% complete. A part of the foundation for the highest crane on the construction site is ready.

Here you can see how the buildings look now.