Wrocław, 12 March 2015
The progress of works carried out at Moderno Estate is estimated at 57% . The structure of the buildings has been completed, including the curtain walls. Some of the retaining walls at the west part of the building have been completed. Roof chimneys have been constructed and insulated. Insulation of the roof surface has started and the roof is 30% complete. Underground garage ceiling has been insulated and PVC window joinery is now installed. Works on aluminium window joinery and aluminium front façades are in progress. A scaffolding is being erected in order to start the insulation works on the front of the building. Horizontal sections of the sanitary system in the garage are finished and now vertical plumbing and the vent stacks are being installed. Currently, installation works in the apartments (water and sewage systems) and electrical works are carried out. Simultaneously, the plastering layers are being applied inside the apartments and in common areas.
Here you can see how the buildings look now.