FADESA POLNORD POLSKA
Flats you want to live in
 

PROGRESS OF CONSTRUCTION WORKS IN B4 BUILDING – FEBRUARY 2015

Warsaw, 10 March 2015

FPP informs that:

B4 building is 45% complete. The excavation , drainage, reinforced concrete structures and insulation of the underground parts are 100% completed, the backfill is 99% complete, the bricklaying - 90%, the roof insulation - 60%, external systems (sewage system and storm water drainage, water supply) are 80% complete, sanitary systems and ventilation are 20% complete, whereas the electrical systems are 10% complete.

Here you can see how the buildings look now.

Marketing and Sales Department


Sales Office opening hours during Easter Week
Contact | Privacy Policy | Fadesa Polnord Polska
© Fadesa Polnord Polska Sp. z o.o.
Ta strona używa COOKIES.

Korzystając z niej wyrażasz zgodę na wykorzystywanie cookies, zgodnie z ustawieniami Twojej przeglądarki.

Akceptuję