Warsaw, 7 April 2015
FPP informs that:
B4 building is 48% complete. The excavation , drainage, reinforced concrete structures and insulation of the underground parts are 100% completed, the backfill is 99% complete, the bricklaying - 95%, the roof insulation - 70%, external systems (sewage system and storm water drainage, water supply) are 80% complete, sanitary systems and ventilation are 30% complete, whereas the electrical systems are 20% complete.
Here you can see how the buildings look now.