Warsaw, 16/10/2015
Ladies and Gentlemen,
The percentage of completion of the buildings C2 is 34%. The reinforced concrete structure has been completed in 95%, the insulation of the underground part of the building in 95%. Backfilling of the building is done in 80%. Masonry work is done in 10%.
Marketing and Sales Department