FADESA POLNORD POLSKA
Flats you want to live in
 

THE PROGRESS OF CONSTRUCTION WORKS IN APARTAMENTY INNOVA III IN WROCLAW IN THE 6.2 BUILDING IS AT THE LEVEL OF 13% AND 6% IN THE 6.1 BUILDING

Wrocław, 12.07.2017

FPP informs that:

The progress of works in the 6.2 building is at the level of 13% while in the 6.1 building at the level of 6%.

So far the land has been developed and the temporary access roads have been built as well as the dig out for the foundation slab to protect the dig out as well as the diaphragm wall and the platform for heavy machinery performing the construction works of the diaphragm wall. The construction works of the diaphragm wall have been completed - it was dug out, reinforced and all the sections have been covered with concrete along the circumference for buildings  6.2 i 6.1. The top plate of the diaphragm wall has been carried out together with the connectors to the reinforced concrete wall in the 6.2 and 6.1 building. The excavation works for the 6.2 building have been finalised, the stretchers for the diaphragm walls have also been installed. The excavation works for 6.1 building are being finalised with the works being 90% complete. The foundation works have been started. The layer of the basis concrete has been added ('lean concrete') under the 6.2 building. On it the waterproof insulation has been added as well as the works on reinforcing the foundation slab have been started.

Marketing and Sales Department


Sales Office opening hours during Easter Week
Contact | Privacy Policy | Fadesa Polnord Polska
© Fadesa Polnord Polska Sp. z o.o.
Ta strona używa COOKIES.

Korzystając z niej wyrażasz zgodę na wykorzystywanie cookies, zgodnie z ustawieniami Twojej przeglądarki.

Akceptuję