FADESA POLNORD POLSKA
Flats you want to live in
 

THE PROGRESS OF CONSTRUCTION WORKS IN APARTAMENTY INNOVA III IN WROCLAW IN THE 6.2 BUILDING IS AT THE LEVEL OF 18% AND 8% IN THE 6.1 BUILDING

Wrocław, 11.08.2017

FPP informs that:

The progress of works in the 6.2 building is at the level of 18% and 8% in the 6.1 building.

The area has been developed, temporary access roads have been prepared and the excavation for the foundation plate as well as the diaphragm and the platform for heavy machinery performing the works on the diaphragm wall are now ready. The construction of the diaphragm wall has come to an end - it was dug out, reinforced and all the sections have been covered with concrete. The top plate of the diaphragm wall has been carried out together with the connectors to the reinforced concrete wall in the 6.2 and 6.1 building. The excavation works for the 6.2 and 6.1 buildings have been finalized, the stretchers for the diaphragm walls have also been installed. The works on the foundations have been started.

6.2 building

The layer of the basis concrete has been added ('lean concrete') under the 6.2 building. On it the waterproof insulation has been added as well as the works on reinforcing the foundation slab have been started. The foundation slab has been covered with concrete, the insulation of the expansion joint of the building has been done just like the circumferential insulation of the foundation slab. Elements made of reinforced concrete are being added on the foundation slab (reinforced concrete walls and pillars) on the -2 floor which has been done in 80%. The works on the formwork for the ceiling above the -2 level have also started.

6.1 building

The layer of the basis concrete has been added ('lean concrete') under the 6.1 building. On it the waterproof insulation has been added. The foundation slab has also been completed. The works on reinforcing the foundation slab are in progress. The first part of the slab has been covered with concrete. The reinforcements have been done and the deeper parts of the slab have been covered with concrete. The reinforcing is taking place on the remaining part of the slab - the works have been done in 75%. The reinforcing of the pillars on the -2 level has been completed in that part of the slab.

Marketing and sales department


Sales Office opening hours during Easter Week
Contact | Privacy Policy | Fadesa Polnord Polska
© Fadesa Polnord Polska Sp. z o.o.
Ta strona używa COOKIES.

Korzystając z niej wyrażasz zgodę na wykorzystywanie cookies, zgodnie z ustawieniami Twojej przeglądarki.

Akceptuję