Wrocław, 13.10.2017
FPP informs that:
The progress of works in the 6.2 building is at the level of 28% and 22% in the 6.1 building.
The area has been developed, temporary access roads have been prepared and the excavation for the foundation plate as well as the diaphragm and the platform for heavy machinery performing the works on the diaphragm wall are now ready. The construction of the diaphragm wall has come to an end - it was dug out, reinforced and all the sections have been covered with concrete. The top plate of the diaphragm wall has been carried out together with the connectors to the reinforced concrete wall in the 6.2 and 6.1 building. The excavation works for the 6.2 and 6.1 buildings have been finalized, the stretchers for the diaphragm wall have also been installed. The works on the foundations have been completed.
6.2 building
The layer of the basis concrete has been added ('lean concrete') under the 6.2 building. On it the waterproof insulation has been added as well as the works on reinforcing the foundation slab have been started. The foundation slab has been covered with concrete, the insulation of the expansion joint of the building has been done just like the circumferential insulation of the foundation slab. Elements made of reinforced concrete have been added on the foundation slab (reinforced concrete walls and pillars) on the -2 floor including the ceiling of the 02 level. The drive-in ramp at the -1 level to -2 as well as from level 0 to -1 has been done. Elements made of reinforced concrete have been completed on the -1 and -2 levels (reinforced concrete walls and pillars). The works on the ceiling of the 0 level are currently ongoing. Clapboard works are ongoing as are the works on reinforcing the floor above the 0 level.
6.1 building
The layer of the basis concrete has been added ('lean concrete') under the 6.1 building. On it the waterproof insulation has been added. The foundation slab has also been completed. The works on reinforcing the foundation slab have been completed. The reinforcements have been done (walls, pillars) of the -2 level and -1 level together with the ceilings. The reinforcing is taking place above the 0 level have been done in approx. 70%. The reinforcing works above the 0 level have been completed in approx. 40% of the ceiling above level 0.
Marketing and Sales department