Wrocław, 8 June.2017
FPP informs that:
The progress of works in the 6.2 building is at the level of 6% and 3% in the 6.1 building.
The process of land development has been completed, temporary access roads and the excavation for the foundation plates of buildings and its protection, diaphragm wall as well as the platform for heavy machinery used to build the diaphragm wall have been put in place.The construction of the diaphragm wall has been completed - it was dug out, reinforced and all the sections have been filled with concrete - around the entire perimeter of buildings 6.2 and 6.1. The top plate of the diaphragm wall has been done together with the elements for the reinforced concrete wall for buildings 6.2 and 6.1. The excavation works for 6.2 building from the side of the 6.3 building have been started, the stretchers of the diaphragm wall have been installed at the construction site of the 6.3 building.
The foundation for the crane has been performed.