FADESA POLNORD POLSKA
Flats you want to live in
 

THE PROGRESS OF CONSTRUCTION WORKS IN THE 6.3 BUILDING IN APARTAMENTY INNOVA II IN WROCLAW IS AT THE LEVEL OF 75%.

Wrocław, 11.08.2017

FPP informs that:

The progress of works in the 6.3 building is at the level of 75%.

The construction of the building has been performed - the reinforced concrete works. The walls, pillars as well as floor headers up to floor +17 together with the ceiling above the floor +17. The reinforced concrete firewalls of the roof, the walls and the lift shafts have been completed. The bricklaying works are nearly done. Dividing as well as curtain walls from 1 to 17 floor are done. PVC windows have been put up. Internal plastering of flats has been done on floors 1-16, there are still works to be done on floor +17. The surfaces for floors on floors 1-14, 16 and 17 have been done, floor 15 is still yet to come. The painting works are being continued - wall whitening has been done on floors 2-10.  Insulation works of corridor walls in flats are ongoing as well as those of staircases made of mineral wool as well as the insulation works of balconies and loggias - metal works and separation layer. Works on the roof are also ongoing - the insulation has been done, the pressure layer - concrete levelling and insulation layer has been put up. Works outside of the building are also ongoing - external scaffolding has been put up and thermal insulation of the roof is currently in progress - Styrofoam and mineral wool (floors 1 - 17). 95% of the east side has been done, 95% of the west side, 75% of the north one and 90% of the south one. The mesh reinforcement is also being done just like the plaster coating. The railings of balconies are being installed on an ongoing basis. Sanitary installations are also being done - water, sewage and heating in the garage, water supply, sewage and heating in flats and electrical works - cabling - has been done up to floor +17. Tele technical network of the building is being done on an ongoing basis.

Ventilation installation of the building is being done - up the floor +17. Installation accessories are also being installed - fire dampers, pressure boosters, central, electrical distribution panels, etc. The installation of heaters as well as mechanical ventilation fans is ongoing.

The second phase of network works is now completed - sanitary and storm water drainage as well as works relating to central heating network and the district heating substation. The reinforced holding tank has been installed.

Marketing and sales department


Sales Office opening hours during Easter Week
Contact | Privacy Policy | Fadesa Polnord Polska
© Fadesa Polnord Polska Sp. z o.o.
Ta strona używa COOKIES.

Korzystając z niej wyrażasz zgodę na wykorzystywanie cookies, zgodnie z ustawieniami Twojej przeglądarki.

Akceptuję