Warsaw, 8 June 2017
FPP informs that the:
progress of works in the B2 building is at the level of 77%.
The foundation plate has been completed in 100%, the walls of basements together with the basement ceilings, insulation of basement walls as well as vertical elements starting from the ground floor to fourth floor as well as ceilings of all floors and walls starting from the ground floor to fourth floor have been completed in 100%. The plastering works have been completed in 95% likewise the windows. Sanitary and electrical installations have been completed in 80% while the floors in 95%, tiles in staircases in 90%, entrance doors in 90% and sills in 95%. The facade of the building has been completed in 50% and the backfill in 100%.